Denmark makes history with massive offshore wind farm tender

Christian Wenande
December 3rd, 2021


This article is more than 3 years old.

Thor Havvindmøllepark will be the biggest of its kind in Denmark and the first to be built without state funding

The farm will be situated off the west coast of Denmark (photo: Danish Energy Agency)

The Energy Ministry has announced that Thor Wind Farm has won the tender to construct the huge offshore wind farm Thor Havvindmøllepark.

It will be the first time that an offshore wind farm project will be completed without state funding in Denmark – in fact, the state will receive 2.8 billion kroner when the farm begins to produce energy.

“The Thor Havvindmøllepark tender is another milestone in Danish offshore wind history,” said Kristoffer Böttzauw, the head of the Danish Energy Agency.

“It is the first time ever that money will be paid to the state to establish offshore wind. More impressive about the tender price is that the erector must pay for the landing link themselves for the first time. It really promises good things for future offshore wind tenders and the green transition.”

READ ALSO: Denmark’s biggest offshore wind farm ready for action

Supplying 1 million homes 
Thor Havvindmøllepark is the first of three offshore wind farms to be produced as part of the Energy Agreement from 2018.

It will become the biggest offshore wind farm in Denmark and is expected to produce energy from about 2026.

Situated at least 22 km off the west coast of Denmark, it will produce 800-1,000 MW and supply electricity to about 1 million Danish households.

It is estimated that investment expenditure for the wind park will be around 15.5 billion kroner. 

The tender stipulates that Thor Havvindmøllepark must be fully functional by the end of 2027 at the latest.

Read more about the project here (in English).

Earlier this year, Denmark reached another climate milestone when its biggest offshore wind farm to date, Kriegers Flak, was ready to begin supplying the country with sustainable electricity.


Share

Most popular

Subscribe to our newsletter

Sign up to receive The Daily Post

















Latest Podcast

A survey carried out by Megafon for TV2 has found that 71 percent of parents have handed over children to daycare in spite of them being sick.

Moreover, 21 percent of those surveyed admitted to medicating their kids with paracetamol, such as Panodil, before sending them to school.

The FOLA parents’ organisation is shocked by the findings.

“I think it is absolutely crazy. It simply cannot be that a child goes to school sick and plays with lots of other children. Then we are faced with the fact that they will infect the whole institution,” said FOLA chair Signe Nielsen.

Pill pushers
At the Børnehuset daycare institution in Silkeborg a meeting was called where parents were implored not to bring their sick children to school.

At Børnehuset there are fears that parents prefer to pack their kids off with a pill without informing teachers.

“We occasionally have children who that they have had a pill for breakfast,” said headteacher Susanne Bødker. “You might think that it is a Panodil more than a vitamin pill, if it is a child who has just been sick, for example.”

Parents sick and tired
Parents, when confronted, often cite pressure at work as a reason for not being able to stay at home with their children.

Many declare that they simply cannot take another day off, as they are afraid of being fired.

Allan Randrup Thomsen, a professor of virology at KU, has heavily criticised the parents’ actions, describing the current situation as a “vicious circle”.

“It promotes the spread of viruses, and it adds momentum to a cycle where parents are pressured by high levels of sick-leave. If they then choose to send the children to daycare while they are still recovering, they keep the epidemic going in daycares, and this in turn puts a greater burden on the parents.”