Danish engineering behind Taiwanese offshore wind turbine park

Stephen Gadd
June 27th, 2018


This article is more than 6 years old.

Consulting engineers COWI are in the process of designing 32 jacket foundations for Taiwan’s first offshore wind turbine park

Tropical cyclones from 1980-2005 over South China and Taiwan. Bad weather is a major problem the engineers have to face (photo: NASA/Joint Typhoon Warning Centre/Nilfanion)

There are a lot of challenges when you are building offshore, as Danish consulting engineer firm COWI has discovered in the process of a project being built off Taiwan’s west coast.

When in place, the turbines will have to be able to withstand earthquakes, typhoons and waves over 20 metres high, reports Ingeniøren.

“Actually, it is the natural forces that really make the Formosa I project especially challenging,” said Jan Rønberg, marketing director for COWI’s global offshore wind sector.

The project has also been evolving along the way, as new data has become available and new technological advances have been made.

Building up their own expertise
The Taiwanese are also anxious to build up their expertise within the offshore wind industry field through using local firms and these companies don’t yet have all the expertise that can be found in Europe.

“One thing is to establish whether to use monopiles or three or four-legged jackets when there is a lack of local knowledge. Something else is that you have to take into consideration in southeast Asia is whether local firms can make the items you want,” added Rønberg.

When completed, the Formosa I project will deliver 130 MW and cover an area of around 11 square km around 3-6 km off the west coast of Taiwan.

The turbines will be 100 metres high and the foundations have been designed to cope with wind speeds of up to 250 km/per hour and serious earthquakes.

Two of the 32 turbines are already up and running and serving as prototypes for the rest. The complete park is expected to be finished in 2019.


Share

Most popular

Subscribe to our newsletter

Sign up to receive The Daily Post

















Latest Podcast

A survey carried out by Megafon for TV2 has found that 71 percent of parents have handed over children to daycare in spite of them being sick.

Moreover, 21 percent of those surveyed admitted to medicating their kids with paracetamol, such as Panodil, before sending them to school.

The FOLA parents’ organisation is shocked by the findings.

“I think it is absolutely crazy. It simply cannot be that a child goes to school sick and plays with lots of other children. Then we are faced with the fact that they will infect the whole institution,” said FOLA chair Signe Nielsen.

Pill pushers
At the Børnehuset daycare institution in Silkeborg a meeting was called where parents were implored not to bring their sick children to school.

At Børnehuset there are fears that parents prefer to pack their kids off with a pill without informing teachers.

“We occasionally have children who that they have had a pill for breakfast,” said headteacher Susanne Bødker. “You might think that it is a Panodil more than a vitamin pill, if it is a child who has just been sick, for example.”

Parents sick and tired
Parents, when confronted, often cite pressure at work as a reason for not being able to stay at home with their children.

Many declare that they simply cannot take another day off, as they are afraid of being fired.

Allan Randrup Thomsen, a professor of virology at KU, has heavily criticised the parents’ actions, describing the current situation as a “vicious circle”.

“It promotes the spread of viruses, and it adds momentum to a cycle where parents are pressured by high levels of sick-leave. If they then choose to send the children to daycare while they are still recovering, they keep the epidemic going in daycares, and this in turn puts a greater burden on the parents.”